ERCOT large-load queue
Historical snapshot ·
ERCOT source report- Requested
- 466 GW
- Approved to energize
- 8.9 GW
- Observed energized
- 5.7 GW
Snapshot scope and data
Queue figures are a historical snapshot, not a current queue census. The tracked queue reached 12.2× its 2022 size by June 18, 2026. Each point comes from a reviewed ERCOT report. View source data.ERCOT's Large Load Integration pagecarries process materials, including the C/D question guide. The RFIs in RIOO are controlling documents.
From request to energization
Studies, agreements, security postings, and transmission separate a request from energization.
Everything below fits inside the first 12 GW of the rail above: the bracketed sliver. Magnified 39× so it can be read.
How to read this snapshot. The 3.9 GW June non-simultaneous monthly peak of loads approved to energize is a different measure from the Observed Energized tier. ERCOT announced a pause in further approvals for large-load data centers and crypto facilities of 75 MW or greater, effective August 3, 2026. See the Batch Zero process and later status. SPP is tracked separately.
Queue history
The tracked queue total, one point per ERCOT LLI Queue Status deck, since 2022.
The Batch Zero clock
The PUCT granted ERCOT's good-cause exceptions on August 20, 2026. ERCOT targeted August 31 forconditional classification notices. ERCOT later reported sending classifications to TSPs on September 3 in Project 59142 Item 55. Customer receipt and final inclusion remain unverified. Full detail and the §25.194 record are on the Batch Zero page.
Project-record review · synthetic example
A project decision needs its own records.
The public queue shows the market. It cannot establish whether one named project has the required evidence. In a synthetic review, Pallara linked candidate facts to exact project-record passages, withheld two conflicting LLIS completion dates, and identified the evidence needed to resolve them.
This demonstrates software behavior on two invented records. It is not a customer result, a complete project review, or an authorized decision.
The candidate review leaves the completion date empty. Its next step is to obtain authoritative completion evidence or an explicit correction before using either date.
Inspect both source passages, the seven proposed observations, the withheld conflict, and the limits of this evaluation.
Preston only. Describe the calculation; do not email private contracts, bills, or meter data. No agent replies.
- [·] Sources: ERCOT LLWG report, June 2026 · NPRR1325 · ERCOT's good-cause requests, PUCT Project 59142 (2026-08-10) and ERCOT's update in the same project (2026-08-20), for the energization pause and its scope. Every figure links to its primary document; the full dataset is on Data.