ERCOT large-load queue

Historical snapshot ·

ERCOT source report
Requested
466 GW
Approved to energize
8.9 GW
Observed energized
5.7 GW
Snapshot scope and data

Queue figures are a historical snapshot, not a current queue census. The tracked queue reached 12.2× its 2022 size by June 18, 2026. Each point comes from a reviewed ERCOT report. View source data.ERCOT's Large Load Integration pagecarries process materials, including the C/D question guide. The RFIs in RIOO are controlling documents.

From request to energization

Studies, agreements, security postings, and transmission separate a request from energization.

Requested· tracked queue
~466GW

Everything below fits inside the first 12 GW of the rail above: the bracketed sliver. Magnified 39× so it can be read.

Approved to energize· cleared studies
8,926MW
1.9% of requested
Observed energized· ERCOT tier
5,700MW
1.2% of requested
Tracked queue at Jun '26; approved-to-energize and Observed Energized per the ERCOT LLWG report, June 2026. The 3,900 MW June non-simultaneous monthly peak of loads approved to energize is a different measure, not this energized tier. Upper rail at true scale, lower rail magnified 39×.

How to read this snapshot. The 3.9 GW June non-simultaneous monthly peak of loads approved to energize is a different measure from the Observed Energized tier. ERCOT announced a pause in further approvals for large-load data centers and crypto facilities of 75 MW or greater, effective August 3, 2026. See the Batch Zero process and later status. SPP is tracked separately.

Queue history

The tracked queue total, one point per ERCOT LLI Queue Status deck, since 2022.

Tracked large-load queue total, 38.1 GW (2022-09) → 466 GW (2026-06)0100200300400500GW2023202420252026+172 GW · 2026-0338.1 GW · 2022-09466GW2026-06 · 12.2×
Tracked queue total, one point per ERCOT LLI Queue Status deck (Sep 26, 2022 → Jun 18, 2026). Source URLs, SHA-256, and methodology on the Data page.

The Batch Zero clock

The PUCT granted ERCOT's good-cause exceptions on August 20, 2026. ERCOT targeted August 31 forconditional classification notices. ERCOT later reported sending classifications to TSPs on September 3 in Project 59142 Item 55. Customer receipt and final inclusion remain unverified. Full detail and the §25.194 record are on the Batch Zero page.

ERCOT states it will file the Batch Zero Eligibility Verification Report and the Community Impact Review Report on this date. ERCOT's pause on further approvals to energize Large Load data centers and virtual currency mining facilities runs “until the verification has been completed”, so this filing is the first stated point at which that pause could lift. This is ERCOT's announced plan in its 2026-08-20 filing in PUCT Project 59142, not an adopted rule deadline or a PUCT order.December 10, 2026 · ERCOT announced · source
T−12days
The Commission open meeting ERCOT identifies for its Batch Zero Eligibility Verification Report and Community Impact Review Report. This is ERCOT's announced plan in its 2026-08-20 filing in PUCT Project 59142. No PUCT order sets this date, and no outcome for any project follows from the meeting being scheduled.December 17, 2026 · ERCOT announced
T−19days

Full Batch Zero clock

Project-record review · synthetic example

A project decision needs its own records.

The public queue shows the market. It cannot establish whether one named project has the required evidence. In a synthetic review, Pallara linked candidate facts to exact project-record passages, withheld two conflicting LLIS completion dates, and identified the evidence needed to resolve them.

This demonstrates software behavior on two invented records. It is not a customer result, a complete project review, or an authorized decision.

Example Campus · invented records2 datesone unresolved LLIS completion event

The candidate review leaves the completion date empty. Its next step is to obtain authoritative completion evidence or an explicit correction before using either date.

Inspect both source passages, the seven proposed observations, the withheld conflict, and the limits of this evaluation.

Preston only. Describe the calculation; do not email private contracts, bills, or meter data. No agent replies.