466 gigawatts requested.
5.7 observed energized.

ERCOT's tracked large load queue has grown about 12.2× since 2022. Most is data center load. Requested, approved, and Observed Energized are separate figures from the Jun '26 snapshot (source age 70 days as of August 27, 2026). The 3.9 GW June non-simultaneous monthly peak of loads approved to energize is a different measure. Since 2026-08-03 ERCOT has paused further approvals to energize Large Load data centers and crypto facilities of 75 MW or greater, so the approved-to-energize stage these figures describe is not currently open to most of this load — see the Batch Zero clock. SPP's regime is tracked separately on the SPP page.

Requested is not built

Between a queue request and a running load sit studies, agreements, security postings, and transmission. The distance between these three numbers is the whole story.

Requested· tracked queue
~466GW

Everything below fits inside the first 12 GW of the rail above: the bracketed sliver. Magnified 39× so it can be read.

Approved to energize· cleared studies
8,926MW
1.9% of requested
Observed energized· ERCOT tier
5,700MW
1.2% of requested
Tracked queue at Jun '26; approved-to-energize and Observed Energized per the ERCOT LLWG report, June 2026. The 3,900 MW June non-simultaneous monthly peak of loads approved to energize is a different measure, not this energized tier. Upper rail at true scale, lower rail magnified 39×.

The line to plug into Texas

The tracked queue total, one point per ERCOT LLI Queue Status deck, since 2022.

Tracked large-load queue total, 38.1 GW (2022-09) → 466 GW (2026-06)0100200300400500GW2023202420252026+172 GW · 2026-0338.1 GW · 2022-09466GW2026-06 · 12.2×
Tracked queue total, one point per ERCOT LLI Queue Status deck (Sep 26, 2022 → Jun 18, 2026). Source URLs, SHA-256, and methodology on the Data page.

The Batch Zero clock

The PUCT granted ERCOT's good-cause exceptions on August 20, 2026. ERCOT intends to notify each interconnecting DSP or TSP of conditional classifications by August 31, starting the dispute and reconciliation process in Planning Guide §9.3.1(2)(a)(i)-(iii). August 31 is not final inclusion or a final classification date. Full detail and proposed §25.194 capital terms are on the Batch Zero page.

QSA prerequisite gate for Q2-2027 energizationNovember 1, 2026 · scheduled · source
T−42days
ERCOT states it will file the Batch Zero Eligibility Verification Report and the Community Impact Review Report on this date. ERCOT's pause on further approvals to energize Large Load data centers and virtual currency mining facilities runs “until the verification has been completed”, so this filing is the first stated point at which that pause could lift. This is ERCOT's announced plan in its 2026-08-20 filing in PUCT Project 59142, not an adopted rule deadline or a PUCT order.December 10, 2026 · ERCOT announced
T−81days

Full Batch Zero clock

Public evidence example

See what the public record can support.

The public queue shows the market. It cannot show whether one named project has the required evidence. This frozen research example shows the source evidence, contradictions, unknowns, and public facts that would change the estimate. Radar changes can trigger new simulations or shadow decisions; they do not authorize production action or establish customer readiness.

Cipher Colchis18%at least 75 MW by 2028 Q2

Eight quarterly horizons show the estimated chance of energization and expected energized MW.

This first vintage is prior_only: intentionally wide, not calibrated, not a claim of ERCOT approval, and not based on private customer evidence.