Readiness register

What reviewed public sources establish about named large loads in ERCOT, and what they do not. Gaps are published as gaps.

9 projects15 cited facts24 record statements46 open unknowns

Basis

  1. Public sources only. Company disclosures, official pages, ERCOT and PUCT records.
  2. Every value carries its source, its measurement basis, and its retrieval date.
  3. Facts absent from reviewed sources are recorded as unknown. Nothing is inferred.
  4. A company's statement is recorded as that company's statement, not as an ERCOT determination.
  5. Total power capacity, design capacity and approved interconnect capacity are distinct quantities. None of them is aggregate peak Demand.

Cipher Colchis

Cipher Digital Inc. (NASDAQ: CIFR) · BZ-01, BZ-04

Decision questionDoes the July 24 Batch Zero TSP-to-ERCOT submission deadline apply to Colchis, and if it does, which submissions remain open?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Crusoe Stargate 1 Abilene

Crusoe · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Stargate 1 Abilene, and which Crusoe or Lancium owner holds each required fact and record?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Galaxy Helios

Galaxy Digital Inc. (NASDAQ: GLXY) · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Helios, and which project facts and records resolve the screen?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Rowan Temple

Rowan Digital Infrastructure · BZ-01, BZ-04

Decision questionWhich of the three Batch Zero dates bind Temple, the July 24 TSP-to-ERCOT submission, the conditional August 1 Q1-2027 QSA prerequisite gate, and the currently unknown ERCOT classification date, and what must be true for each to matter? August 7 remains the adopted deadline ERCOT says it will miss; August 20 is only a PUCT process checkpoint.

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Sabey SDC Austin

Sabey Data Centers · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to SDC Austin, and which project facts and records resolve the screen?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Satoshi Dragon Goby

Satoshi Energy · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Dragon Goby, and which site-boundary, Demand, exemption, and evidence facts resolve the screen?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Skybox PowerCampus Dallas

Skybox Datacenters · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements (PUCT-approved 2026-07-09, effective 2026-08-01) apply to PowerCampus Dallas, and which project facts resolve the screen?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

STACK DFW02

STACK Infrastructure · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to DFW02, and which project facts and records resolve the screen?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source

Tract Caldwell Valley

Tract · RT-02

Decision questionDo the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Caldwell Valley, and which site-boundary, Demand, exemption, and evidence facts resolve the screen?

Cited public facts

Public record statements

Open unknowns, not established by any reviewed public source