Readiness register

Source-linked facts and open questions for named ERCOT large-load projects.

Open project workspace

9 projects16 cited facts25 record statements46 open unknowns

How to read the evidence
  1. Public sources only. Company disclosures, official pages, ERCOT and PUCT records.
  2. Every value carries its source, its measurement basis, and its retrieval date.
  3. Facts absent from reviewed sources are recorded as unknown. Nothing is inferred.
  4. A company's statement is recorded as that company's statement, not as an ERCOT determination.
  5. Total power capacity, design capacity and approved interconnect capacity are distinct quantities. None of them is aggregate peak Demand.

Cipher Colchis

Cipher Digital Inc. (NASDAQ: CIFR) · BZ-01, BZ-04

Project grid Eight-quarter forecast
Reported capacity
1,000 MW
Signed direct connect agreement with AEP
Company target
2028
Subject to ERCOT’s batch study process
ERCOT status
Unconfirmed
Interconnection phase and Batch Zero participation

Cited public facts

Public record statements (2)
Open questions (4)

Decision question. Does the July 24 Batch Zero TSP-to-ERCOT submission deadline apply to Colchis, and if it does, which submissions remain open?

  • Batch Zero participation, Cipher's filings put Colchis "subject to ERCOT batch study process," but no public source shows whether the July 10 ILLE package was filed or accepted; whether it went in is now a fixed fact only Cipher's interconnection owner can confirm.
  • Eligibility path (standard study, PCLR election, or WLPUN/BYOG), not public; the July 24 TSP package contents depend on it.
  • Interconnecting-TSP role, the Direct Connect Agreement counterparty is AEP, but the interconnecting TSP responsible for the July 24 TSP-to-ERCOT qualification package is not confirmed in any public source.
  • Completed submissions, no public record shows which Batch Zero submissions, if any, are already in; no submission status is asserted here.
Back to project index

Crusoe Stargate 1 Abilene

Crusoe · RT-02

Project grid

Cited public facts

Public record statements (6)
Open questions (4)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Stargate 1 Abilene, and which Crusoe or Lancium owner holds each required fact and record?

  • Applicability, total power capacity and approved interconnect capacity do not establish RT-02 applicability without the rule's project-specific facts.
  • Evidence, no ride-through capability evidence, exemption record, or computational-share documentation has been reviewed.
  • Crusoe/Lancium responsibility boundary, the public division of labor does not allocate the RT-02 facts, filings, evidence, or compliance ownership between the companies.
  • Single-site scope, the separate adjacent 900 MW campus and projected 2.1 GW full Abilene site do not establish the RT-02 single-site boundary for Stargate 1 or its aggregate peak Demand.
Back to project index

Galaxy Helios

Galaxy Digital Inc. (NASDAQ: GLXY) · RT-02

Project grid

Cited public facts

Public record statements (2)
Open questions (5)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Helios, and which project facts and records resolve the screen?

  • Applicability, approved power capacity and completed LLIS work do not establish RT-02 applicability without the rule's project-specific facts.
  • Aggregate peak Demand, the public 1.63 GW approved-power figure is not a declaration of aggregate peak Demand at the single site.
  • Computational share of site Demand, not stated in the reviewed public sources.
  • Exemption or grandfathering, no reviewed public source confirms either.
  • Evidence, no ride-through capability evidence, exemption record, or computational-share documentation has been reviewed.
Back to project index

Rowan Temple

Rowan Digital Infrastructure · BZ-01, BZ-04

Project grid

Cited public facts

Public record statements (1)
Open questions (5)

Decision question. Which of the three Batch Zero dates bind Temple, the July 24 TSP-to-ERCOT submission, the conditional August 1 Q1-2027 QSA prerequisite gate, and the currently unknown ERCOT classification date, and what must be true for each to matter? August 7 remains the adopted deadline ERCOT says it will miss; August 20 is only a PUCT process checkpoint.

  • Whether Temple is being submitted through Batch Zero at all, the July 10 ILLE filing window has closed, so whether the package went in is now a fixed fact only Rowan can confirm; public information does not show it.
  • Eligibility path (standard study, PCLR election, or WLPUN/BYOG), not public; the supporting materials due with the July 24 TSP package depend on it.
  • Whether Initial Energization in January to March 2027 is targeted , "operations 2027" is year-only, so the August 1 QSA prerequisite gate cannot be resolved from public information.
  • The interconnecting TSP's identity for §9 purposes, the Oncor power partnership is public, but the interconnecting-TSP role for the July 24 TSP-to-ERCOT package is Rowan's to confirm with Oncor.
  • ERCOT study status and completed submissions, not public; no submission or owner is asserted here.
Back to project index

Sabey SDC Austin

Sabey Data Centers · RT-02

Project grid

Cited public facts

Public record statements (2)
Open questions (5)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to SDC Austin, and which project facts and records resolve the screen?

  • Applicability, published campus power and critical IT capacities do not establish RT-02 applicability without the rule's project-specific facts.
  • Aggregate peak Demand, the public 84 MW capacity figure is not a declaration of expected aggregate peak Demand at the single site.
  • Computational share of site Demand, not stated in the reviewed public source.
  • Exemption or grandfathering, no reviewed public source confirms either.
  • Project state and evidence, no study, agreement, ride-through capability, exemption, or computational-share record has been reviewed.
Back to project index

Satoshi Dragon Goby

Satoshi Energy · RT-02

Project grid

Cited public facts

Public record statements (4)
  • 01

    Satoshi Energy's Projects page lists Dragon Goby as Exclusive LOI, with Size 500 MW, COD 2030, and market ERCOT. These are developer-reported values observed on November 19, 2026. The date the card changed is unknown.

    Satoshi Energy Projects: Dragon Goby card · verified · 2026-11-19

  • 02

    In the July 29, 2026 snapshot, Satoshi Energy's former Dragon Goby card listed Development, Size 475 MW, COD Q4 2026, and market ERCOT.

    Former Satoshi Energy development page (https://satoshienergy.com/development, now unavailable) · verified · 2026-07-29

  • 03

    In the July 29, 2026 snapshot, Satoshi Energy described development and marketing of construction-ready sites and offered colocated-development services generally. The Dragon Goby card did not identify the project as colocated.

    Former Satoshi Energy development page (https://satoshienergy.com/development, now unavailable) · verified · 2026-07-29

  • 04

    Satoshi Energy Corp. filed comments in PUCT Project 58481 on April 16, 2026. Its 476 MW energized-with-renewables, 5 GW ERCOT pipeline, nearly 2 GW completed-study, and zero-CIAC statements are company-wide and do not name Dragon Goby, so none is attributed to this project.

    PUCT Project 58481, Item 156: Satoshi Energy Corp. comments · verified · 2026-07-29

Open questions (7)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Dragon Goby, and which site-boundary, Demand, exemption, and evidence facts resolve the screen?

  • Applicability, the developer's size label does not establish RT-02 applicability without a location, single-site boundary, aggregate peak Demand, computational share, and exemption facts.
  • Project identity and request, the owner, operator, customer, and ILLE legal entities; location; site boundary; whether the request is new or expanded; request date; meaning of the size label; requested peak Demand; contracted Demand; aggregate peak Demand; and computational MW or fraction are not public.
  • Interconnection path, the TSP, DSP, POI, substation, request or LLIS number, study phase, status, results, Intermediate Agreement, Interconnection Agreement, and whether Dragon Goby is within Satoshi's company-wide pipeline, completed-study, or zero-CIAC sets are not established by the reviewed sources.
  • Batch Zero, reviewed sources do not verify qualification, filing, classification, route, allocation, deficiency status, Forms W or X, Affiliate Attestation, PCLR status, WLPUN status, a prior dynamic-stability study, or a Section 9.2.1.4 eligibility route.
  • Demand and energization records, commercial operation, exact Initial Energization, ramp, current LIF or LCP, site-control proof, duplicate-project and backup-generation disclosures, QSA, NTP, and telemetry remain unverified.
  • Capital, construction, and generation, fees, security, CIAC, long-lead commitments, colocated-generation status, export, and netting are not public project facts. The general colocated-development service does not establish colocation at Dragon Goby.
  • Ride-through, no NOGRR282 exemption or frequency- and voltage-ride-through evidence is public. No DWG, dynamic, steady-state, stability, or short-circuit evidence has been reviewed.
Back to project index

Skybox PowerCampus Dallas

Skybox Datacenters · RT-02

Project grid

Cited public facts

Public record statements (3)
Open questions (4)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements (PUCT-approved 2026-07-09, effective 2026-08-01) apply to PowerCampus Dallas, and which project facts resolve the screen?

  • Computational share of site demand, public information does not show whether the planned load mix meets the >= 50% Large Computational Load threshold (NPRR1308 definition).
  • Aggregation, the 300 MW figure is Skybox's listed available power, not a declaration of aggregate peak Demand at the single site; whether energized demand will meet the definition's >= 75 MW aggregate-peak-Demand test as stated is for Skybox to confirm.
  • Exemption / grandfathering, no public record shows whether a NOGRR282 ride-through exemption or grandfathering has been confirmed for this campus.
  • Evidence, no ride-through capability evidence, exemption record, or computational-share documentation has been reviewed; this is a public-information first pass.
Back to project index

STACK DFW02

STACK Infrastructure · RT-02

Project grid

Cited public facts

Public record statements (1)
Open questions (5)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to DFW02, and which project facts and records resolve the screen?

  • Applicability, advertised campus capacity does not establish RT-02 applicability without the rule's project-specific facts.
  • Aggregate peak Demand, the public 500 MW figure is not a declaration of expected aggregate peak Demand at the single site.
  • Computational share of site Demand, not stated in the reviewed public source.
  • Exemption or grandfathering, no reviewed public source confirms either.
  • Project state and evidence, no current phase, executed agreement, milestone, ride-through capability, exemption, or computational-share record has been reviewed.
Back to project index

Tract Caldwell Valley

Tract · RT-02

Project grid

Cited public facts

Public record statements (4)
  • 01

    Tract labels Caldwell Valley "Owned & In Development," lists 2,973 acres, states site energization "in 2028," and describes multiple campus options on 345-kV transmission lines. The year-only energization label is not an exact Initial Energization date or a ramp schedule.

    Tract project page: Caldwell Valley · verified · 2026-07-29

  • 02

    Tract says the full roughly 3,000-acre park can support more than 4 GW of data-center capacity; Tract, Bluebonnet Electric Cooperative, and LCRA are planning an onsite substation capable of scaling to 1.6 GW; and the first 250 MW of capacity is contracted for delivery in Q1 2028. These are distinct public measurement labels, not Demand declarations or proof of the parties' ERCOT interconnection roles.

    Tract announcement: Caldwell Valley incremental acquisitions · verified · 2026-07-29

  • 03

    The same announcement says Tract initiated plans for onsite generation that would become grid connected. It does not establish current generation, WLPUN status, export, netting, or an ERCOT interconnection.

    Tract announcement: Caldwell Valley incremental acquisitions · verified · 2026-07-29

  • 04

    Tract Holding Company I LLC filed comments in PUCT Project 58481 on April 13, 2026. Its 2.8 GW proposed, 6.2 GW ultimate, four-project, three-TSP, and advanced-LLIS statements are company-wide and do not name Caldwell Valley, so none is attributed to this project.

    PUCT Project 58481, Item 141: Tract Holding Company I LLC comments · verified · 2026-07-29

Open questions (7)

Decision question. Do the NOGRR282/NPRR1308 Large Computational Load ride-through requirements apply to Caldwell Valley, and which site-boundary, Demand, exemption, and evidence facts resolve the screen?

  • Applicability, capacity, substation-scale, acreage, and delivery labels do not establish RT-02 applicability without a defined single-site boundary, aggregate peak Demand, computational share, and exemption facts.
  • Project identity and request, the owner or ILLE legal entity, whether the request is new or expanded, its request date, requested peak Demand, contracted Demand, aggregate peak Demand, and the campus division of the public 4 GW capacity label are not public.
  • Interconnection path, the TSP, DSP, POI, request or LLIS number, study phase, status, results, Intermediate Agreement, Interconnection Agreement, and whether Caldwell Valley is among Tract's four company-wide LLIS projects are not established by the reviewed sources. Bluebonnet's and LCRA's ERCOT regulatory roles cannot be inferred from the announcement.
  • Batch Zero, no public source establishes filing, classification, route, allocation, deficiency status, Forms W or X, Affiliate Attestation, PCLR or WLPUN status, a prior dynamic-stability study, or a Section 9.2.1.4 eligibility route.
  • Demand and energization records, exact Initial Energization, ramp, current LIF or LCP, site-control proof, duplicate-project and backup-generation disclosures, QSA, NTP, telemetry, and energization evidence have not been reviewed.
  • Capital and construction, fees, security, CIAC, long-lead commitments, the legal nature and counterparties of the first 250 MW delivery label, and current onsite-generation, WLPUN, export, or netting status are not public project facts.
  • Ride-through, the computational MW or fraction, NOGRR282 exemption, and frequency- and voltage-ride-through evidence are not public. No DWG, dynamic, steady-state, stability, or short-circuit evidence has been reviewed.
Back to project index