PGRR145 / NPRR1325 · the batch study process

The Batch Zero clock.

On 2026-06-02 the ERCOT Board approved PGRR145/NPRR1325 — the revision package that ends the serial large-load study process and replaces it with batches.[1] Recommended effective 2026-07-11, pending PUCT, which takes the package up on 2026-07-09. Eight days after that PUCT meeting, the first hard deadline lands. Miss it and a project is excluded from Batch Zero.

§ 01

Where the package stands

2026-06-02 ERCOT Board approves PGRR145/NPRR1325 board report
2026-07-09 PUCT takes up the protocol package (Project 59142) docket 59142
2026-07-11 Recommended effective date for Batch Zero and WLPUN NPRR1325 · PGRR145
§ 02

Every milestone, on a live clock

Batch Zero · next milestone · July 9, 2026
T−24DAYS

PUCT takes up ERCOT's Batch Zero protocol package (PGRR145/NPRR1325) at open meeting. The package is Board-approved and recommended effective 2026-07-11; this is the approval gate.

source document

Date Clock Milestone Status Source
Jul 9, 2026 T−24 PUCT takes up ERCOT's Batch Zero protocol package (PGRR145/NPRR1325) at open meeting. The package is Board-approved and recommended effective 2026-07-11; this is the approval gate. scheduled interchange.puc.texas.gov
Jul 10, 2026 T−25 ILLE submission deadline: study/dynamic-model data plus eligibility materials due. Missed means excluded from Batch Zero. Also the last day for legacy LLIS approvals under the current serial process. pending PUCT ercot.com
Jul 24, 2026 T−39 TSP/DSP qualification packages due — attestations, disclosures, financial-security confirmations — plus PCLR Form W Part A (notarized, binding minimum LCP per study year) for projects electing the provisional pathway. pending PUCT ercot.com
Aug 7, 2026 T−53 ERCOT issues deficiency notifications on submitted qualification packages. pending PUCT ercot.com
Aug 31, 2026 T−77 Final inclusion cut — the Batch Zero study roster is fixed. Excluded projects wait for Batch 1 (potential case build June 2027). pending PUCT ercot.com
Apr 9, 2027 T−298 Batch Zero final report and MW allocation. Allocated MW reserved against restudy; the commitment gate (interconnection agreement plus financial commitments) converts allocation to firm. pending PUCT ercot.com

Dates from the PGRR145 Board Report (2026-06-02), verified against the June 1–2, 2026 Board materials. “Pending PUCT” means the deadline sits inside the Board-approved package and takes effect subject to PUCT approval. Day counts are end-of-day Central time.

§ 03

How the batch study works, in plain English

Until now, every large load (≥75 MW) was studied one at a time, in the order it showed up — a serial queue that produced the 410-GW pile-up. Batch Zero studies everyone who qualifies at once.[1]

Get in. By 2026-07-10, an interconnecting large-load entity must submit its study and dynamic-model data plus eligibility materials. That date is also the last day for legacy approvals under the serial process. By 2026-07-24, the transmission or distribution provider files the qualification package — attestations, disclosures, financial-security confirmations — and projects electing the PCLR pathway file Form W Part A (notarized and binding). ERCOT flags incomplete packages by 2026-08-07; the roster is fixed at the final inclusion cut, 2026-08-31.

Get studied. ERCOT studies the batch as a group and publishes the final report with MW allocations on 2027-04-09. Allocated MW is reserved against restudy; a commitment gate — signed interconnection agreement plus financial commitments — converts an allocation to firm, and non-committed projects are automatically removed. The minimum allocation threshold is roughly 100 MW (90% for requests of 100 MW or less).[1]

Or get curtailable power sooner. The PCLR election (Provisional Controllable Load Resource) trades firmness for speed: firm service up to a load-commitment limit, with consumption above it curtailable via SCED dispatch, ahead of transmission buildout. It is not an eligibility bypass, and the obligations run with the facility.[1]

Miss it, wait. Projects excluded from Batch Zero wait for Batch 1 — a potential case build in June 2027.[1]

Proposed — not adopted

The money attached to a request, as proposed under 16 TAC §25.194 (PUCT Project 58481). The docket shows no adoption order — these numbers bind nobody yet, and the docket is the place to watch.[2]

$100k / $300k
Study fee — $100,000 for 75–249 MW; $300,000 at 250 MW and above.
$50k per MW
Financial security, roughly 20% refundable on withdrawal.
$50k per MW
Non-refundable interconnection fee on contracted demand, with staged refunds over five years of operation.

A 300-MW data center under the proposal: $300k study fee + $15M security + $15M interconnection fee. Source: proposed rule text, docket 58481 (203 filings and counting; watch the docket for the order, not law-firm alerts for a date).