# The source registry. Every URL lli-radar watches, with cadence and why it matters.
# Verified 2026-06-06 (LLI-BUILD-PLAN audit); re-verify dates noted per entry.
# This file is the product's spine: ingest/watch.py reads it, the site cites it.

version: 1
updated: "2026-06-11"

sources:
  - id: lli_queue_status
    name: LLI Queue Status Update / TAC reports
    what: >
      Aggregate large-load queue: MW by status tier, zone, TSP, project type,
      size bucket, submittal and in-service date distributions. The only public
      queue data; NPRR1267 (PUCT-approved 2025-07-31) mandates aggregation.
    format: PDF slide decks
    cadence: roughly monthly, tied to TAC/LLWG meetings; history to Oct 2022
    urls:
      - https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf
    url_pattern: "https://www.ercot.com/files/docs/YYYY/MM/DD/LLI%20Queue%20Status%20Update%20-%20*.pdf"
    feeds: data/queue_timeseries.csv

  - id: llwg
    name: Large Load Working Group hub
    what: Agendas and decks; "Large Load Interconnection Queue" is a standing agenda item.
    format: HTML page linking PDF/PPTX
    cadence: "monthly (2026: Jan 22, Feb 19, Mar 13, Apr 24, May 21, Jun 19, Jul 23)"
    urls:
      - https://www.ercot.com/committees/tac/llwg
    ical: "webcal://www.ercot.com/ical/meetings?host_id=llwg"
    feeds: data/manifest.json

  - id: tac
    name: Technical Advisory Committee hub
    what: TAC meeting pages carry the LLI Queue Status report when LLWG skips a month.
    format: HTML page linking PDF/PPTX
    cadence: monthly
    urls:
      - https://www.ercot.com/committees/tac
    feeds: data/manifest.json

  - id: lli_hub
    name: Large Load Integration hub
    what: >
      Forms and process docs: Load Information Form v1 (xlsx), Energization
      Request (docx), Net Metering Notice (docx), LLI Q&A (pdf), comms
      instructions. Changes here signal process changes.
    format: HTML page linking forms
    cadence: updated on process changes
    urls:
      - https://www.ercot.com/services/rq/large-load-integration
    feeds: data/manifest.json

  - id: planning_guide_s9
    name: "Planning Guide §9 — Large Load Additions"
    what: Governing interconnection rule text. Current text dated 2025-12-15.
    format: DOCX
    cadence: on revision (PGRRs)
    urls:
      - https://www.ercot.com/mktrules/guides/planning/current
      - https://www.ercot.com/files/docs/2011/04/28/09-121525.docx
    feeds: data/manifest.json

  - id: batch_zero
    name: PGRR145 / NPRR1325 (Batch Zero)
    what: >
      Board-approved 2026-06-02, recommended effective 2026-07-11, pending PUCT
      (taken up 2026-07-09). Deadlines: 2026-07-10 ILLE submissions, 2026-07-24
      TSP qualification + PCLR Form W Part A, 2026-08-07 deficiency notices,
      2026-08-31 final inclusion cut, 2027-04-09 final report + MW allocation.
    format: DOCX board report + issue tracker pages
    cadence: per revision-request status change
    urls:
      - https://www.ercot.com/mktrules/issues/NPRR1325
      - https://www.ercot.com/mktrules/issues/PGRR145
      - https://www.ercot.com/files/docs/2026/06/02/145PGRR-116-Board-Report-060226.docx
    feeds: data/deadlines.yaml

  - id: puct_58481
    name: "PUCT Project 58481 (proposed §25.194 — large load interconnection standards)"
    what: >
      Proposed rule + all comments. 203 filings as of 2026-06-05, no adoption
      order yet. Proposal: $100k/$300k study fees, $50k/MW security (~20%
      refundable), $50k/MW interconnection fee. Watch the docket for the order;
      do not assert an adoption date.
    format: JS-rendered docket (needs headless scrape)
    cadence: daily watch
    urls:
      - https://interchange.puc.texas.gov/Search/Filings?ControlNumber=58481
      - https://interchange.puc.texas.gov/Documents/58481_122_1600475.PDF
    feeds: data/filings/58481.json

  - id: puct_59142
    name: PUCT Project 59142 (large-load batch study process)
    what: PGRR145/NPRR1325 protocol-package filings land here. PUCT consideration 2026-07-09.
    format: JS-rendered docket
    cadence: daily watch
    urls:
      - https://interchange.puc.texas.gov/Search/Filings?ControlNumber=59142
    feeds: data/filings/59142.json

  - id: puct_sb6_satellites
    name: Adjacent SB 6 dockets
    what: >
      58479 net metering, 58480 forecasting (§25.370, effective 2026-03-01),
      58482 demand reduction, 58484 4CP.
    format: JS-rendered dockets
    cadence: daily watch
    urls:
      - https://interchange.puc.texas.gov/Search/Filings?ControlNumber=58479
      - https://interchange.puc.texas.gov/Search/Filings?ControlNumber=58480
      - https://interchange.puc.texas.gov/Search/Filings?ControlNumber=58482
      - https://interchange.puc.texas.gov/Search/Filings?ControlNumber=58484
    feeds: data/filings/

  - id: market_notices
    name: ERCOT market notices archive
    what: "LLI process notices (e.g. M-B062325-01 DWG survey, M-B090225-01 net metering, M-B021126-01 RFIs)."
    format: HTML archive + email lists
    cadence: daily watch
    urls:
      - https://www.ercot.com/services/comm/archives
    feeds: data/manifest.json

terms:
  redistribution: >
    ERCOT Terms of Use §5 (verified verbatim 2026-06-06): raw data provided in
    public portions of the website may be used, reproduced, and redistributed
    in compilations, charts, and analyses. No commercial-use prohibition.
  prohibitions:
    - Do not use the ERCOT logo (Terms §9).
    - Do not republish project-level customer data (none is public; NPRR1267).