SPP large load interconnection.

Requests, inferred tracks, and executed agreements.

Request record swept Aug 27, 2026

Public-record sweep

0executed agreements

Required CHILLSA and HILLGIA public filings.

Verification

13 / 13sources cleared

Checked Aug 27, 2026 at 22:37 UTC

What SPP shows

All 17 share one status: preliminary assessment complete, SPP study required.

17 public request records
Public SPP requests with inferred HILL or CHILL tracks
RequestReceivedAgeTrack
DPA-2026-February-2281-HHILL inferred
DPA-2026-March-2294-HHILL inferred
DPA-2026-March-2301-HHILL inferred
DPA-2026-March-2307-HHILL inferred
DPA-2026-March-2316-HHILL inferred
DPA-2026-April-2325-HHILL inferred
DPA-2026-April-2329-HHILL inferred
DPA-2026-May-2337-HHILL inferred
DPA-2026-May-2339-HHILL inferred
DPA-2026-May-2342-HHILL inferred
DPA-2026-May-2343-HHILL inferred
DPA-2026-May-2345-HHILL inferred
DPA-2026-May-2349-HHILL inferred
DPA-2026-June-2362-HHILL inferred
DPA-2026-June-2366-HHILL inferred
DPA-2026-June-2376-HHILL inferred
DPA-2026-July-2381-CHCHILL inferred
Why we read H as HILL
  • 2024 and 2025 postings: 385 requests, zero suffixes
  • first -H received 2026-02-05; HILL effective 2026-01-15
  • first -CH received 2026-07-24; CHILLS effective 2026-07-01
  • all 16 -H and the 1 -CH require a study; unsuffixed are mixed

SPP publishes no suffix key.

Not listed? SPP keeps other pending requests private.

Trace a request

Test a site

Voltage
Dedicated generation

Filing steps, cash, and clocks

    Cash

    ItemBasisAmount

    Clocks

    CHILLS service

    0 to 7 years

    Miss either one year deadline and CHILLS ends. The maximum term is seven years. An HDPLA expires after one year.2

    Proof

    Primary sources
    RuleCoversOrder
    HILL and HILLGADefinitions, fees, filing, and clocks194 FERC ¶ 61,031 (ER26-247)
    CHILLSTerm and termination clocks195 FERC ¶ 61,196 (ER26-1323)
    Open caseaccession not capturedUpgrade costs and co location terms195 FERC ¶ 61,213 (EL26-68-000)

    Not read: the August 17 response filings and the EL26 accession. The accepted orders were subject to condition. No figure fills that gap.