Weekly · Mondays 07:00 CT

The digest.

Once a week: what changed at ERCOT (new decks, changed forms), what landed on the dockets, what the time series did, and the next 30 days of deadlines. The numbers are injected from the committed dataset — the model writes the prose, never the figures.

§ 01

Archive

2026-07-06

The week in data — 2026-07-06 (numbers-only edition)

Numbers-only edition: the deterministic weekly context, published without narration. Every line is generated from the committed data.

This issue was published without narration — no LLM was available to the weekly action. Every line below comes deterministically from the committed data; a narrated issue resumes when the key is restored.

META

Today (digest date): 2026-07-06
Digest issue number: 3
Diff baseline: commit that published 2026-07-01.md [640bafbec804]

ABOUT LLI-RADAR (standing facts, primary-source verified)

lli-radar

The public record of ERCOT's large-load interconnection queue, assembled from primary sources nobody else maintains.

ERCOT tracks ~466 GW of requested large load (~90% data centers) but publishes the queue only as aggregate MW in PDF slide decks tied to TAC/LLWG meetings — 8,926 MW approved to energize, only 3,900 MW observed operating, a 0.8% funnel from request to reality (June 2026 LLI status update). There is no machine-readable time series, no consolidated regulatory feed, and ERCOT's own Large Load Portal (targeted end-2026) will be customer-facing, not public. lli-radar fills that gap with three things:

  1. The queue time series — every LLI Queue Status deck since October 2022, extracted into one clean dataset (data/queue_timeseries.csv).
  2. The regulatory radar — Batch Zero milestone countdown (PGRR145/NPRR1325), PUCT docket filing feeds (58481, 59142, and the SB 6 satellites), LLWG/TAC material watch.
  3. The weekly digest — what changed, in plain English, with the numbers injected from the data, not generated.

Everything is files in git. No database, no backend, no auth. The repo history is the audit trail.

BATCH ZERO CLOCK / UPCOMING DEADLINES (next 30 days flagged)

  • 2026-07-11 (5 days away) [WITHIN 30 DAYS]: Recommended effective date for Batch Zero and WLPUN (PCLR effective upon system implementation). From the NPRR1325/PGRR145 issue pages. (status: scheduled)
  • 2026-07-10 (4 days away) [WITHIN 30 DAYS]: ILLE submission deadline: study/dynamic-model data plus eligibility materials due to the interconnecting TSP/DSP. Missed means excluded from Batch Zero. Also the last day for legacy LLIS approvals under the current serial process. (status: scheduled)
  • 2026-07-24 (18 days away) [WITHIN 30 DAYS]: TSP/DSP qualification packages due to ERCOT — attestations, disclosures, financial-security confirmations — plus PCLR Form W Part A (notarized, binding minimum LCP per study year) for projects electing the provisional pathway. (status: scheduled)
  • 2026-08-07 (32 days away): ERCOT issues deficiency notifications on submitted qualification packages. Date is from the June 5 timeline deck, not the live ERCOT LLI page — lower confidence. (status: projected)
  • 2026-08-31 (56 days away): Final inclusion cut — the Batch Zero study roster is fixed. Excluded projects wait for Batch 1 (potential case build June 2027). Date is from the June 5 timeline deck, not the live ERCOT LLI page — lower confidence. (status: projected)
  • 2027-01-29 (207 days away): Batch Zero study results and MW allocation. Allocated MW reserved against restudy; the commitment gate (interconnection agreement plus financial commitments) converts allocation to firm. Date is projected from secondary sources (study results ~Jan 2027, IA execution ~Mar 2027) — ERCOT has not published a primary-source final-report date. (status: projected)

ERCOT DOCUMENTS (new/changed since baseline, from data/manifest.json)

PUCT FILINGS (new since baseline, from data/filings/*.json)

No new PUCT filings since the baseline.

QUEUE TIME SERIES (data/queue_timeseries.csv, newest report vs prior)

Newest report_date: 2026-06-18; prior report_date: 2026-05-20

  • Large Load Queue — Co-Located (latest snapshot 2026-06): 69708 MW
  • Large Load Queue — Standalone (latest snapshot 2026-06): 396789 MW
  • Large Load Queue — Total (latest snapshot 2026-06): 466497 MW
  • No Studies Submitted: 257600 MW (prior 307700 MW, change -50100 MW)
  • Under ERCOT Review: 151100 MW (prior 75400 MW, change +75700 MW)
  • Section 9.4 Requirements Only: 11800 MW (prior 9300 MW, change +2500 MW)
  • Section 9.4/9.5 Requirements Met: 37100 MW (prior 37100 MW, change +0 MW)
  • A2E but not operational: 3200 MW (prior 2000 MW, change +1200 MW)
  • Observed Energized: 5700 MW (prior 7100 MW, change -1400 MW)
  • Total (GW) — full queue projection: 466500 MW (prior 438600 MW, change +27900 MW)
  • Under ERCOT Review (studies in progress or complete): 151100 MW (prior 75400 MW, change +75700 MW)
  • Section 9.4 Requirements Only (studies in progress or complete): 11800 MW (prior 9300 MW, change +2500 MW)
  • Section 9.4/9.5 Requirements Met (studies in progress or complete): 37100 MW (prior 37100 MW, change +0 MW)
  • A2E but not operational (studies in progress or complete): 3200 MW (prior 2000 MW, change +1200 MW)
  • Observed Energized (studies in progress or complete): 5700 MW (prior 7100 MW, change -1400 MW)
  • Total (GW) — studies in progress or complete: 208900 MW (prior 130800 MW, change +78100 MW)
  • ERCOT Approvals — Section 9.4 (latest snapshot 2026-06): 11803 MW
  • ERCOT Approvals — Section 9.4/9.5 (latest snapshot 2026-06): 37085 MW
  • ERCOT Approvals — Approved to Energize (latest snapshot 2026-06): 8926 MW
  • ERCOT Approvals — Total (latest snapshot 2026-06): 57814 MW
  • Loads Approved to Energize — Observed Non-Simultaneous Peak Load (latest 2026-06): 3900 MW
  • Loads Approved to Energize — Remaining Approved to Energize (latest 2026-06): 5026 MW
  • Loads Approved to Energize — Total Approved to Energize (latest 2026-06): 8926 MW
  • Loads Approved to Energize — Observed Simultaneous Peak Load (latest 2026-06): 3675 MW
  • Loads Approved to Energize — Remaining Approved to Energize Load (simultaneous chart, latest 2026-06): 5251 MW
  • Loads Approved to Energize — Total (simultaneous chart, latest 2026-06): 8926 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (1) Base Load Eligible: 24900 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (2a) Studies Validated: 8700 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (2b) Potentially Invalid: 4200 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (2c) Under Review: 3000 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (3) Studied/Base Eligible: 9600 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (4) One Study Complete: 46600 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (5) Path to Studied: 97200 MW
  • Batch Zero Tracking by Weather Zone (GWs) — (6) Not Included: 287200 MW
  • Batch Zero Tracking by Weather Zone (GWs) — Total (GW): 481400 MW

2026-07-01

Batch Zero is locked, the queue jumps to ~466 GW, and the ILLE clock reads 9 days

PUCT gave Batch Zero final approval, ERCOT's June status update puts the tracked queue at 466,497 MW after a pre-Batch-Zero data cleanup, and the first Batch Zero eligibility table shows most tracked load not yet on a path in. ILLE submissions are due 2026-07-10.

Read full issue

Batch Zero is locked — 9 days to the ILLE deadline

The PUCT gave final approval to ERCOT's Batch Zero protocol package (PGRR145/NPRR1325); the rule is no longer pending and the deadlines below are binding. The clock now reads:

  • 2026-07-10 (9 days away) — ILLE submissions: study and dynamic-model data plus eligibility materials due to the interconnecting TSP/DSP. Missed means excluded from Batch Zero. Also the last day for legacy LLIS approvals under the serial process.
  • 2026-07-24 (23 days away) — TSP/DSP qualification packages due to ERCOT, plus PCLR Form W Part A for projects electing the provisional pathway.
  • 2026-08-07 (37 days away) — deficiency notifications on submitted qualification packages (projected date).
  • 2026-08-31 (61 days away) — final inclusion cut; the Batch Zero study roster is fixed (projected date).

The queue jumps to 466,497 MW — and the studies surge is on

ERCOT's June LLI status update (data current as of 2026-06-18) puts the tracked large-load queue at 466,497 MW — Standalone 396,789 MW, Co-Located 69,708 MW — against 438,600 MW in the prior report (2026-05-20), a change of +27,900 MW on the GW-rounded funnel. Two movements inside that total tell the real story:

  • Under ERCOT Review roughly doubled: 151,100 MW, up +75,700 MW from 75,400 MW. With the ILLE deadline days away, loads are racing to get studies in front of ERCOT.
  • No Studies Submitted fell: 257,600 MW, down -50,100 MW from 307,700 MW — projects either started studies or were cleaned out. ERCOT notes it scrubbed the LLIS data ahead of Batch Zero, removing cancelled and duplicate tickets and combining multi-stage requests into single LLI numbers.

The cleanup also touched the approval tiers: Approved to Energize now reads 8,926 MW, with an observed non-simultaneous monthly peak of 3,900 MW and an observed simultaneous peak of 3,675 MW. "A2E but not operational" rose to 3,200 MW (+1,200 MW) while "Observed Energized" in the projection table fell to 5,700 MW (-1,400 MW) — tier reshuffles consistent with the duplicate-ticket removal, not load disappearing.

First look: the Batch Zero eligibility table

The June update adds something new: a Batch Zero tracking table by weather zone, the first public cut of who is actually positioned for the batch. Across 481,400 MW tracked in the table:

  • Not Included (unless studies start soon): 287,200 MW
  • Path to Studied: 97,200 MW
  • One Study Complete: 46,600 MW
  • Base Load Eligible: 24,900 MW
  • Studied/Base Eligible: 9,600 MW
  • Studies Validated: 8,700 MW
  • Potentially Invalid: 4,200 MW
  • Under Review: 3,000 MW

Read plainly: the bulk of tracked load is not yet on a path into Batch Zero, and the window closes 2026-07-10.

On the docket

  • Project 59142 — comments on PGRR145 landed from Crusoe Technologies (2026-06-12), CyrusOne (2026-06-16), and First Ammonia (2026-06-17), all filed around the approval.
  • Project 58484 — Chairman Drew Darby filed a letter regarding evaluation of transmission cost recovery (2026-06-30).

Housekeeping

This issue covers three weeks: the weekly action had been failing silently since the 2026-06-11 issue (a missing API key). The pipeline is fixed and now publishes a numbers-only edition rather than skipping a week when narration is unavailable. Every figure above comes from the committed dataset — the June deck's rows are in data/queue_timeseries.csv, each carrying its source URL and content hash.

2026-06-11

lli-radar #1: The Queue Nobody Else Publishes, and a 28-Day Clock to Batch Zero

The inaugural issue of lli-radar introduces the project, takes first inventory of the documents and dockets we now watch, and starts the Batch Zero countdown — with the first PUCT approval gate 28 days away.

Read full issue

Why this digest exists

lli-radar is the public record of ERCOT's large-load interconnection queue, assembled from primary sources nobody else maintains.

ERCOT tracks roughly 410 GW of requested large load — about 87% of it data centers — but publishes the queue only as aggregate MW in PDF slide decks tied to TAC/LLWG meetings. Within those decks: 9,042 MW approved to energize, but only 3,883 MW observed operational — a 1.6% funnel from request to reality. There is no machine-readable time series, no consolidated regulatory feed, and ERCOT's own Large Load Portal (targeted end-2026) will be customer-facing, not public.

lli-radar fills that gap with three things: the queue time series (every LLI Queue Status deck since October 2022, extracted into one dataset), the regulatory radar (Batch Zero milestone countdown, PUCT docket feeds, LLWG/TAC material watch), and this weekly digest — what changed, in plain English, with numbers injected from the data, not generated. Everything is files in git; the repo history is the audit trail.

This is issue #1. With the repo younger than seven days and no prior digest, there is no diff baseline yet — everything below is a first inventory.

The current queue picture

From ERCOT's published slide decks: about 410 GW of requested large load, roughly 87% of it data centers. Against that, 9,042 MW are approved to energize, and 3,883 MW are observed operational — the 1.6% funnel from request to reality.

These are the headline figures we will track over time once the deck extraction pipeline is live (see the closing section).

The Batch Zero clock

Two deadlines fall within the next 30 days:

  • 2026-07-09 (28 days away): The PUCT takes up ERCOT's Batch Zero protocol package (PGRR145/NPRR1325) at open meeting. The package is Board-approved and recommended effective 2026-07-11; this is the approval gate.
  • 2026-07-10 (29 days away): ILLE submission deadline — study/dynamic-model data plus eligibility materials due. Missed means excluded from Batch Zero. It is also the last day for legacy LLIS approvals under the current serial process.

Further out:

  • 2026-07-24 (43 days away): TSP/DSP qualification packages due — attestations, disclosures, financial-security confirmations — plus PCLR Form W Part A for projects electing the provisional pathway.
  • 2026-08-07 (57 days away): ERCOT issues deficiency notifications on submitted qualification packages.
  • 2026-08-31 (81 days away): Final inclusion cut — the Batch Zero study roster is fixed. Excluded projects wait for Batch 1 (potential case build June 2027).
  • 2027-04-09 (302 days away): Batch Zero final report and MW allocation. Allocated MW is reserved against restudy; the commitment gate converts allocation to firm.

What we watch weekly

ERCOT documents. First inventory stands at 14 documents now watched — all 14 in the lli_hub set (data/manifest.json). Future issues report additions and changes against this baseline.

PUCT dockets. First inventory across the dockets on our radar:

  • Docket 58479: 67 filings on record, spanning 2025-07-31 to 2026-03-26. Most recent includes a PUC OPDM order adopting new 16 TAC §25.205 (2026-03-26) and Vistra Corp.'s comments on PGRR145 (2026-03-20).
  • Docket 58480: 59 filings, spanning 2025-07-31 to 2026-02-09. Most recent includes a PUC OPDM order adopting new 16 TAC §25.370 (2026-02-06).
  • Docket 58481: 203 filings, spanning 2025-07-31 to 2026-04-20. Recent comments from Cormint Data Systems (2026-04-20) and Mission Power on the IA security posting framework (2026-04-17).
  • Docket 58482: 27 filings, spanning 2025-08-01 to 2026-04-14, including CyrusOne, LP comments (2026-04-08).
  • Docket 59142: 36 filings, spanning 2025-12-17 to 2026-05-26, including Data Center Coalition comments on net metering arrangements in Batch Zero (2026-05-14).

The queue time series. Honest status: data/queue_timeseries.csv is not yet present — the deck extraction is still being built. Until it lands, the queue numbers above come from the published decks and we cannot yet show week-over-week movement. We will say so plainly until the pipeline is live.

Expect future issues to report changes against these baselines: new and changed ERCOT documents, new docket filings, the Batch Zero countdown, and — once extraction ships — the queue time series itself.