| Event date | Status | Milestone | Evidence |
|---|---|---|---|
| complete | PUCT gave final approval to ERCOT's Batch Zero protocol package (PGRR145/NPRR1325) on 2026-06-18. The issue pages read "Approved on 06/18/2026." This establishes the adopted revision package; each later milestone's status below controls whether its date remains operative. | Open | |
| scheduled | ILLE submission deadline, two tracks: forms, attestations, and eligibility materials due to the interconnecting TSP/DSP; the §9.2.2(3) dynamic-model submission due to ERCOT directly (BatchZero@ercot.com by 2359 CDT, per market notice M-B062326-04). Missed means excluded from Batch Zero. Also the hard close of the legacy LLIS process. No further legacy study or restudy approvals. | Open | |
| scheduled | Recommended effective date for Batch Zero and WLPUN (PCLR effective upon system implementation). From the NPRR1325/PGRR145 issue pages. | Open | |
| scheduled | Two distinct July 24 flows, per the live LLI page routing table and market notice M-B062326-04. (1) Interconnecting TSPs/DSPs submit completed Large Load Interconnection details to ERCOT (BatchZero@ercot.com): the Batch Zero LIF workbook, the Interconnecting TSP Dynamic Stability Study Form (where applicable), the Section 9.2.1.4(3)(d) attestation (where applicable), and the forwarded ILLE forms, including notarized Form W Part A (PCLR) and Form X (WLPUN) where elected, which ILLEs filed with their DSP/TSP by July 10. (2) Separately, an ILLE on the Section 9.2.1.2 eligibility path submits its Section 9.2.1.2(1) attestation to its interconnecting DSP/TSP, not to ERCOT, by this same date; that attestation belongs to one eligibility path, not to every ILLE. | Open | |
| scheduled | QSA prerequisite gate for early-2027 energization: an ILLE seeking Initial Energization in January, February, or March 2027 must satisfy all Planning Guide §5.3.5 prerequisites by this date. The governing schedule then expected classifications on Aug 7. After this QSA gate passed, M-A080326-01 announced ERCOT would not issue classifications by the adopted Aug 7 deadline and would seek a good-cause exception. | Open | |
| superseded | ERCOT notifies TSPs/DSPs of Batch Zero classification results, including eligibility determinations and identified dynamic-model or data deficiencies. 2026-08-07 is the adopted Planning Guide §9.3.1(2)(a) deadline (ERCOT market notice M-B062326-04, 2026-07-08). ERCOT did not meet it. On 2026-08-20 the PUCT granted ERCOT a good-cause exception from the deadline and allowed ERCOT to continue reviewing dynamic-data submissions after August 7, with the same 24-day cure period running from notice of a deficiency. The August 7 classification date is retained here as history, not as an operative deadline. | Open | |
| ERCOT announced | ERCOT intends to notify interconnecting DSPs/TSPs of each Large Load's conditional classification by this date. The conditional notice starts the dispute and reconciliation process in Planning Guide §9.3.1(2)(a)(i)-(iii). This is ERCOT's announced target in market notice M-A080326-02, not a new adopted rule deadline. | Open | |
| superseded | The June 5 timeline deck projected a final inclusion cut on this date. Later primary-source actions changed the Batch Zero process. The August 20 PUCT order granted ERCOT's good-cause exceptions, and M-A080326-02 now uses August 31 for conditional-classification notices. Do not treat the older final-inclusion-cut marker as an operative deadline. | Open | |
| scheduled | QSA prerequisite gate for Q2-2027 energization: an ILLE seeking Initial Energization in April, May, or June 2027 must satisfy all Planning Guide §5.3.5 prerequisites by this date. The 2026-08-20 PUCT order lets ERCOT include Large Loads it conditionally classifies as base load in this assessment before final classification. In its 2026-08-20 filing ERCOT put 17 Large Loads, approximately 6,874 MW, as potentially eligible. Inclusion in a QSA does not by itself authorize energization, and approvals to energize remain paused for Large Load data centers and virtual currency mining facilities. | Open | |
| ERCOT announced | ERCOT states it will file the Batch Zero Eligibility Verification Report and the Community Impact Review Report on this date. ERCOT's pause on further approvals to energize Large Load data centers and virtual currency mining facilities runs “until the verification has been completed”, so this filing is the first stated point at which that pause could lift. This is ERCOT's announced plan in its 2026-08-20 filing in PUCT Project 59142, not an adopted rule deadline or a PUCT order. | Open | |
| ERCOT announced | The Commission open meeting ERCOT identifies for its Batch Zero Eligibility Verification Report and Community Impact Review Report. This is ERCOT's announced plan in its 2026-08-20 filing in PUCT Project 59142. No PUCT order sets this date, and no outcome for any project follows from the meeting being scheduled. | Open |