SPP · request record

DPA-2026-March-2307-H · HILL · inferred

Preliminary assessment complete, SPP study required.

Received
First seen
March 2026
Checked
Evidence
March 2026 SPP postingSHA 256 a8c94941c689…
Last change
First appeared in March 2026. SPP marked a study as required. No change through July 2026.
Next action
Submit study agreement materials within 30 calendar days of receiving the preliminary assessment.Risk: SPP withdraws the request if the materials are late, unless both parties agree otherwise.Study timing: SPP has 90 days after the scoping call and complete materials.Source: SPP, Guidelines for Delivery Point Assessments
Not public
SPP does not define the suffix, so the HILL reading is unconfirmed. This record omits the customer, requested MW, connection point, host utility, paired generation, submitted materials, study agreement, results, and reserved capacity.
Watch
SPP posting listSPP posts every request that received a preliminary assessment in the prior month, by the 20th of the succeeding month (Attachment AQ; SPP Guidelines for Delivery Point Assessments).A new file hash marks a change.

HILLGA requests and pending CHILLS applications are absent. Only customer notices can confirm them.

Decision support, not legal advice. Check the posting and current SPP OATT before acting.