ERCOT public record · forecast

STACK DFW02

With no public project timing milestone, the frozen baseline prior assigns a 59% chance that at least 75 MW is energized by 2028 Q2.

Prior-only baseline. It is not calibrated and does not assert ERCOT approval, expected demand, or that any part of the advertised campus capacity will energize on this schedule.

Advertised capacity
Up to 500 MW
Campus marketing value; not expected aggregate peak demand.
By 2028 Q2
59%
19% to 84% sensitivity range

Eight-quarter baseline

Dot: point estimate. Band: wide prior sensitivity range. The range is not a calibrated confidence interval.

Evidence in this vintage

The archived capacity statement supplies project identity and MW context. It does not move the baseline timing curve.

  1. Sets public MW context

    “Secure up to 500MW at STACK’s DFW02 campus”

    Archived sourceSHA 256 aab15f4504c8…

What the public record cannot answer

These gaps are not treated as approvals, rejections, or completed milestones.

  • Applicability, advertised campus capacity does not establish RT-02 applicability without the rule's project-specific facts.
  • Aggregate peak Demand, the public 500 MW figure is not a declaration of expected aggregate peak Demand at the single site.
  • Computational share of site Demand, not stated in the reviewed public source.
  • Exemption or grandfathering, no reviewed public source confirms either.
  • Project state and evidence, no current phase, executed agreement, milestone, ride-through capability, exemption, or computational-share record has been reviewed.
  • Operator page returned HTTP 403 on 2026-08-26; hashed evidence is the Internet Archive original-bytes capture dated 2026-06-16.

Method and reproducibility

The historical cohort contains only 2 labeled projects, too few to fit or backtest a likelihood. Because no public STACK DFW02 timing milestone is present in the frozen ledger, this page uses the explicit no-target baseline prior and a separate cancellation prior. The advertised 500 MW capacity does not shift the timing probabilities and is not converted into expected energized MW. No parameter was fitted to the live watchlist. Cancellation, energized, and remaining-unenergized probabilities sum to 100% in every quarter.

As of
August 26, 2026
Status
prior only
Model
energization-prior-v1
Input hash
12ca4dc88beb7bce7ee68759d015c11d4efd6a6186693c05b95908e71e21aca8
Code commit
50812120f117cb2b3658d8a317a05f4408a07059

Decision support, not legal, engineering, interconnection, or investment advice.