ERCOT public record · forecast

Rowan Temple

By 2028 Q2, the frozen estimate assigns an 62% chance that at least 75 MW is energized.

Prior-only estimate. It is not calibrated and does not assert that ERCOT approved the project. Rowan’s year-only operations target does not establish that at least 75 MW will energize in 2027.

Company target
2027
Year-only operations target; no public quarter or month.
By 2028 Q2
62%
20% to 84% sensitivity range

Eight-quarter distribution

Dot: point estimate. Band: wide prior sensitivity range. The range is not a calibrated confidence interval.

What moved the estimate

Only the target timing and public MW value change the numerical prior. Other reviewed facts remain visible as context.

  1. Sets MW scale

    “construction is underway at its 300-megawatt (MW) Project Temple site”

    Primary sourceSHA 256 d9d0e82aec8f…
  2. Context only

    “power secured through a partnership with Oncor”

    Primary sourceSHA 256 d9d0e82aec8f…
  3. Sets timing prior

    “Operations are expected in 2027”

    Primary sourceSHA 256 d9d0e82aec8f…

What the public record cannot answer

These gaps are not treated as approvals, rejections, or completed milestones.

  • Whether Temple is being submitted through Batch Zero at all, the July 10 ILLE filing window has closed, so whether the package went in is now a fixed fact only Rowan can confirm; public information does not show it.
  • Eligibility path (standard study, PCLR election, or WLPUN/BYOG), not public; the supporting materials due with the July 24 TSP package depend on it.
  • Whether Initial Energization in January to March 2027 is targeted , "operations 2027" is year-only, so the August 1 QSA prerequisite gate cannot be resolved from public information.
  • The interconnecting TSP's identity for §9 purposes, the Oncor power partnership is public, but the interconnecting-TSP role for the July 24 TSP-to-ERCOT package is Rowan's to confirm with Oncor.
  • ERCOT study status and completed submissions, not public; no submission or owner is asserted here.
  • Operator page live retrieval returned HTTP 403 on 2026-08-26; hashed evidence is the Internet Archive original-bytes capture dated 2026-01-17.

Method and reproducibility

The historical cohort contains only 2 labeled projects, too few to fit or backtest a likelihood. The model therefore uses an explicit weak timing prior anchored to Rowan's stated year-only 2027 operations target and a separate cancellation prior. The target is not evidence that at least 75 MW will energize in 2027. No parameter was fitted to the live watchlist. Cancellation, energized, and remaining-unenergized probabilities sum to 100% in every quarter.

As of
August 26, 2026
Status
prior only
Model
energization-prior-v1
Input hash
12ca4dc88beb7bce7ee68759d015c11d4efd6a6186693c05b95908e71e21aca8
Code commit
50812120f117cb2b3658d8a317a05f4408a07059

Decision support, not legal, engineering, interconnection, or investment advice.