PUCT Interchange · public records

The docket feed.

Two dockets decide what large-load interconnection costs and how it works: 58481 (the proposed §25.194 standards — fees and security) and 59142 (the Batch Zero protocol package). Four SB 6 satellites orbit them. The Interchange is JS-rendered and unfeedable; this page is the feed.

§ 01

Watched dockets

DocketWhat it decidesFilingsSource
58481Proposed §25.194 — large-load interconnection standards203interchange.puc.texas.gov ↗
59142Large-load batch study process (PGRR145/NPRR1325 package)41interchange.puc.texas.gov ↗
58479SB 6 — net metering67interchange.puc.texas.gov ↗
58480SB 6 — forecasting (§25.370)59interchange.puc.texas.gov ↗
58482SB 6 — demand reduction33interchange.puc.texas.gov ↗
58484SB 6 — 4CP119interchange.puc.texas.gov ↗
§ 02

Latest filings

showing the 60 most recent of 522 tracked filings · full per-docket JSON on the data page

№ 58482
Jul 16, 2026
item 28
Fedor Mikheev | Texas A&M University Energy Institute
Public Comments in Response to Staff's Questions for Comment - Project No. 58482
№ 59142
Jul 13, 2026
item 41
Trailblazer Infrastrructure LLC.
Notice of Withdrawal – This filing formally withdraws Trailblazer Infrastructure LLC's previously submitted Informational Memorandum in PUCT Project No. 59142. The notice advises the Commission that, due to ongoing discussions among the relevant parties.
№ 59142
Jun 17, 2026
item 39
First Ammonia LLC
First Ammonia LLC's Comments on Commission Consideration of PGRR 145, Batch Zero Process for Large Load Interconnections
№ 58481
Apr 17, 2026
item 176
Permian Basin Petroleum Association
Permian Basin Petroleum Association's Comments in Response to Proposal for Publication of 16 TAC § 25.194
№ 58481
Apr 17, 2026
item 178
CONSTELLATION ENERGY GENERATION, LLC
CONSTELLATION ENERGY GENERATION, LLC’S COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194
№ 58481
Apr 17, 2026
item 183
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER
The Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Proposal for Publication of New 16 TAC § 25.194
№ 58481
Apr 17, 2026
item 201
MISSION POWER
BRIEF COMMENTS IN SUPPORT OF CHAIRMAN GLEESON'S "GRADUAL ESCALATOR FRAMEWORK" FOR GRADUAL POSTING OF THE $50,000 IA SECURITY POSTING