“Our LLIS was completed on September 3, 2026.”Record 1 · line 4
One project.
Two completion dates.
Example Campus records agree that the LLIS was completed. They disagree on when. The candidate review preserves the conflict and leaves the date unresolved.
What the records added
Caller declarations only
The original snapshot names Example Campus, requests 100 MW, and selects the standing-lifecycle profile. It supplies no LLIS fact or completion date.
Claims with inspectable passages
Five observations remain eligible as candidate inputs. Two date observations form one unresolved conflict. The only newly supplied readiness fact is has_llis_completion: true.
The baseline is the recorded original snapshot, not a separately measured before/after performance experiment. Seven observations are not seven distinct facts or seven verified conclusions.
The conflict that changes the next step
“The LLIS was completed on September 9, 2026.”Record 2 · line 3
Result: project_dates.llis_completion is absent from the candidate snapshot. The recorded LLI-04 clock is unverifiable, with no start date or due date. The software has not decided which document is right.
Relevant context the schema cannot express
“The SLLIA has not been signed as of this update.”Record 1 · line 6
The September 14 record plans execution on October 15, 2026 only if commercial terms are agreed. The September 17 record repeats a conditional October 15 signing plan without a year. Neither establishes an executed agreement.
First signing plan · line 5 Later signing plan · line 4The supplied intake has no SLLIA-execution date or signed-agreement fact key. This context comes from the held-out interpreter’s limitation note; it is not represented by the seven structured observations or silently treated as a completed milestone.
Every structured observation
All seven proposals carry assertion status asserted. Eligibility means usable for a candidate assessment, not authenticated or approved.
| No. | Field / value | Disposition | Citation |
|---|---|---|---|
| 01 | project_name"Example Campus" | Candidate input | Record 1 · line 2 |
| 02 | target_mw100 | Candidate input | Record 1 · line 3 |
| 03 | requirement_facts.has_llis_completiontrue | Candidate input | Record 1 · line 4 |
| 04 | project_dates.llis_completion"2026-09-03" | Withheld: conflicting dates | Record 1 · line 4 |
| 05 | project_name"Example Campus" | Candidate input | Record 2 · line 2 |
| 06 | requirement_facts.has_llis_completiontrue | Candidate input | Record 2 · line 3 |
| 07 | project_dates.llis_completion"2026-09-09" | Withheld: conflicting dates | Record 2 · line 3 |
Source records
Both files have the same filename. Source IDs and original-content hashes keep them distinct. Click any citation to open its exact passage. Offsets refer to the supplied parsed block, not byte positions in the original file.
Record 1 Engineering update · September 14project.txt
- Source ID
913c7ab8-91da-4da1-9814-a6a1f0c3e4b0- Original content SHA-256
29f0f20ec24d566838696f1bc24446f820ae4d6be77f21951a68d360ae550d06
SYNTHETIC TEST RECORD. Not a real project or customer.
Passage SHA-256
cd82b51e66060c1ab73b2722a20cd9d1a52eb6b4e05dcdb7051b37f1eee849a9Example Campus engineering update, September 14, 2026.
Passage SHA-256
f5719b6126c1e5b4ba034f14d69633a68a15e45d1eb515481b87ea628a50e297The project requests 100 MW of contracted peak demand.
Passage SHA-256
d4f48b01468de75255143cce19eff9b4b7b04b7881d4a9b70d51dfb18081bbe7Our LLIS was completed on September 3, 2026.
Passage SHA-256
4bfe88c6b09bc5351d9351f211d902990e1e9519a7b69182d939c305ef4a5907We plan to execute the SLLIA on October 15, 2026, if commercial terms are agreed.
Passage SHA-256
741c5325fa22e68b2ec411eed970124bbc074aa72f9147af48b93b6493a6309bThe SLLIA has not been signed as of this update.
Passage SHA-256
2fcf3c2337be2539ac81254bbf4554f0bd7f5fcdde5c473b82daef396fe3f990Record 2 Project manager update · September 17project.txt
- Source ID
525bd880-70ea-489b-ae1d-e28384341de2- Original content SHA-256
6619a023c3943187aba25bfd082f9576ac16d414f7f8e4f8fb80ad9f1ec7d477
SYNTHETIC TEST RECORD. Not a real project or customer.
Passage SHA-256
cd82b51e66060c1ab73b2722a20cd9d1a52eb6b4e05dcdb7051b37f1eee849a9Example Campus project manager update, September 17, 2026.
Passage SHA-256
5dc123ab1fffc350bda1a5bb39cb3cde7d71efacf0f2e9bffce31bfebf21ed65The LLIS was completed on September 9, 2026.
Passage SHA-256
eb1a0c27ce5a63e2edccbd9288b12a8013d26d764bbd9d5cd234fc91bafbcb37The planned October 15 SLLIA signing remains subject to commercial agreement.
Passage SHA-256
5718d22c47f31151251e480b23ebc9a8f35a12cebd1e1916de36cf7e50d86c31What this file proves, and its limits
An inspectable interpretation
A held-out agent read only the API-produced packet and its intake contract. It produced the observations without reading the experiment generator, tests, or expected answers. The review result retained both conflicting dates and omitted a definitive completion date.
Exact citations bind a proposal to supplied text. They do not establish semantic correctness, authenticity, legal sufficiency, submission, acceptance, or project readiness. The requested 100 MW is not proof of contracted capacity or current consumption.
A model-bound candidate result
The result reports model 0.3.24, as of 2026-08-07, and recorded corpus verification 2026-09-07T15:47:28Z. Those stamps are historical metadata, not a live source check on this review date.
The current model requires source verification and applicable-rule review before customer use. This file makes no current regulatory verdict, predicts no deadline, and authorizes no action. The records are synthetic and no customer outcome was validated.
Candidate snapshot and exact provenance
{
"project_name": "Example Campus",
"target_mw": 100,
"requirements_profile": "standing_lifecycle",
"requirement_facts": {
"has_llis_completion": true
},
"project_dates": {}
}Model SHA-25669c283f2a522896de574c2bf0b556035a6fbaf784368fdeaa7e45ac632139387
Assessment evaluated at 2026-09-29T15:19:12.730800-05:00
Decision support, not legal advice. Standalone evaluation artifact; not a production application or a customer deliverable.