# The Batch Zero clock. One entry per milestone; the site countdown reads this file directly.
# Schema (data/SCHEMA.md): {id, date, what, source_url, status}
# Dates verified against cowork/kernel/obligations.yaml v0.2.0 (June 1-2, 2026 Board materials).
# PGRR145/NPRR1325 Board-approved 2026-06-02, recommended effective 2026-07-11, pending PUCT.
# Status values: scheduled (calendared event) | pending_puct (deadline in the Board-approved
# package, effective subject to PUCT approval of the protocol package).

version: 1
updated: "2026-06-11"

deadlines:
  - id: puct-takes-up-package
    date: "2026-07-09"
    what: >
      PUCT takes up ERCOT's Batch Zero protocol package (PGRR145/NPRR1325)
      at open meeting. The package is Board-approved and recommended
      effective 2026-07-11; this is the approval gate.
    source_url: "https://interchange.puc.texas.gov/Search/Filings?ControlNumber=59142"
    status: scheduled

  - id: ille-submission-deadline
    date: "2026-07-10"
    what: >
      ILLE submission deadline: study/dynamic-model data plus eligibility
      materials due. Missed means excluded from Batch Zero. Also the last
      day for legacy LLIS approvals under the current serial process.
    source_url: "https://www.ercot.com/files/docs/2026/06/02/145PGRR-116-Board-Report-060226.docx"
    status: pending_puct

  - id: tsp-qualification-packages
    date: "2026-07-24"
    what: >
      TSP/DSP qualification packages due — attestations, disclosures,
      financial-security confirmations — plus PCLR Form W Part A
      (notarized, binding minimum LCP per study year) for projects
      electing the provisional pathway.
    source_url: "https://www.ercot.com/files/docs/2026/06/02/145PGRR-116-Board-Report-060226.docx"
    status: pending_puct

  - id: deficiency-notices
    date: "2026-08-07"
    what: >
      ERCOT issues deficiency notifications on submitted qualification
      packages.
    source_url: "https://www.ercot.com/files/docs/2026/06/02/145PGRR-116-Board-Report-060226.docx"
    status: pending_puct

  - id: final-inclusion-cut
    date: "2026-08-31"
    what: >
      Final inclusion cut — the Batch Zero study roster is fixed.
      Excluded projects wait for Batch 1 (potential case build June 2027).
    source_url: "https://www.ercot.com/files/docs/2026/06/02/145PGRR-116-Board-Report-060226.docx"
    status: pending_puct

  - id: final-report-mw-allocation
    date: "2027-04-09"
    what: >
      Batch Zero final report and MW allocation. Allocated MW reserved
      against restudy; the commitment gate (interconnection agreement plus
      financial commitments) converts allocation to firm.
    source_url: "https://www.ercot.com/files/docs/2026/06/02/145PGRR-116-Board-Report-060226.docx"
    status: pending_puct